    126126Paint was applied to the tank floor to address a leak in the flume, and the tank floor left to dry and seal. The siphon rig was completed and tested. The laser system was aligned. The position of the basal ADV was refined, Orgasol was required as additional seeding in order for bottom tracking to work effectively. Interesting, the stem (fixed) ADV picks this bottom point up better than the flexible ADV in the absence of seeding. Tested synchronization of ADV with traverse; a problem was identified with the nature of the required input signal. Investigation in progress as to how to address this.
    127127
    128 '''Wednesday September 21st 2016'''
    129 
    130 '''Thursday, September 22nd, 2016'''
    131 
    132128
    133129'''Friday, September 23rd, 2016'''